Limehouse Basin | E14

Brief: Knock through of two rooms to create one family size bathroom, installing fitted cupboards in bedrooms as well as painting and decorating.

The client wanted to knock through two existing small bathrooms and turn into one large family size bathroom. Which involved not only taking down of existing walls but also creating new walls, shower niches, re-plastering of walls and ceiling, tile wall to ceiling, floor tile, the plumbing of new suits, installation of new down lights and new extractor fans.

In addition, RFS Renovation installed new fitted wardrobes to the master bedroom and above bed cupboards for the second bedroom.

Finally, RFS Renovations completed the job by painting and decorating of the new bathroom, master bedroom, second bedroom, kitchen and living area, hallway and Staircase.

Project Duration: 6 weeks and 2 weeks

Completion: August 2017 and February 2018